Fulscot Bridge update

Latest update from Network Rail regarding the bridge works:

We continue to make good progress at Fulscot Road. The current status of the works is as follows:

  • North Capping beam to sheet piles
completed 04/07
  • South capping beam to sheet piles – ongoing
complete by 01/08
  • Soil nail netting (to enable road opening)
completed 04/07
  • Capping beam for augured piles
will complete 07/07
  • Ties (abutment/augured piling cap) back fill
 complete by 10/07
  • L-units (delivery 01/07 onwards)
 complete by 08/07
  • Road works (sub-base/kerbs/drainage)
  complete by 15/08
  • Surfacing
 complete by 22/08
  • Barrier installation
 complete by 29/08
  • Road Open
 2/9/14

We are still on target for opening the road by early September 2014.

Continue reading “Fulscot Bridge update”

Website finally complete

Southmoreton.org.uk is proud to finally say the website is now completely open for use.  All sections are now live and opened up.

Please have a look round, and do provide feedback through either the forum or via email to webmaster@southmoreton.org.uk

We hope this site is useful to you as a source of news and local information.  Please do let us know if you would like anything added, changed, removed etc.

Fulscot Bridge Update

Update from Network Rail:

We continue to make good progress at Fulscot Road. Over the last two weeks the major works are as follows:

  • Capping beam to sheet piles ongoing on northern approach.
  • The laying of the new stone fill material to the embankments is now complete.
  • Northern approach re-grade for soil nails complete (to enable nails to be installed to allow opening of road)
  • Soil nail installation recommenced for southern approach.
  • Augured piling started behind southern abutment
  • Approx 50% BT ducting installed within northern approach
  • Approx. 30% of sheet pile ties installed on northern approach

We are still on target for opening the road by early September 2014.
Continue reading “Fulscot Bridge Update”