Fulscot Bridge update

Latest update from Network Rail regarding the bridge works:

We continue to make good progress at Fulscot Road. The current status of the works is as follows:

  • North Capping beam to sheet piles
Complete
  • South capping beam to sheet piles – ongoing
Complete by 01/08 On target
  • Capping beam for augured piles
Complete
  • Ties (abutment/augured piling cap) back fill
Complete
  • L-units (delivery 01/07 onwards) 28 delivered so far
complete by 21/07
  • Road works (sub-base/kerbs/drainage)
complete by 06/08
  • Surfacing
complete by 22/08 On target
  • Barrier installation
complete by 29/08 On target
  • Road Open
2/9/14 On target

We are still on target for opening the road by early September 2014.

Progress Photos:

140718_01 140718_02140718_03140718_04