Update from Network Rail:
“You will no doubt be pleased to hear that we are very close to completing the works at Fulscot. The remaining works are as follows:
- Parapet walls will be finished Fri 22nd August am
- Surfacing will be finished Friday 22nd August pm
- Road lining Friday 22nd August pm
Following the completion of the works a road safety audit will be undertaken next week.
Subject to the outcome of the road safety audit, we the road will be open by 02/09/14.