Fulscot Bridge update

Update from Network Rail:

“You will no doubt be pleased to hear that we are very close to completing the works at Fulscot. The remaining works are as follows:

  • Parapet walls will be finished Fri 22nd August am
  • Surfacing will be finished Friday 22nd August pm
  • Road lining Friday 22nd August pm

Following the completion of the works a road safety audit will be undertaken next week.

Subject to the outcome of the road safety audit, we the road will be open by 02/09/14.